The onshore cable route for Moray West extends to around 30km and crosses land held by 33 separate landowners. Significant work has gone into seeking voluntary agreement on commercial and material terms with these landowners, but unfortunately the project has not concluded agreements with 2 parties. In order to resolve matters, the project has made a Compulsory Purchase Order (CPO) which will now be submitted to the Scottish Ministers seeking confirmation. To aid public access, the documents relating to this CPO process (including the notice of the making of the Order) are available in the Document Library at Moray West Offshore Wind Farm Document Library